Analyzing Contract Types for Uncertain Projects: Recommendations for the Case Study

Read the case study below and answer ALL the questions that follow Case 2.3: TBD and Erroneous Specifications for a Project We were doing a mooring system project for an offshore oil rig in the Gulf of Mexico. It was a fixed price contract, but the specifications were sprinkled with a lot of TBDs (to be determined) items. As the project manager, the TBDs required a lot of attention and caused tremendous headaches between the customer’s project manager and myself. I had to watch these TBDs like a hawk. When a TBD specification was finalized by the customer, I had to ensure that the clarified specification was doable and that it did not affect my project’s cost and time constraints. Out of a dozen TBD specifications, one was for the smoothness of a stainless steel surface. I had to negotiate this TBD specification rigorously with the customer’s project manager. I did not want to accept a tight specification that would have required extra fine machining of stainless steel surfaces of our system. We first agreed on the smoothness measurement technique and then the measurement sampling location and measurement length for traces. Then we agreed on the maximum Ra value, maximum value of the arithmetic average of absolute values of vertical deviations of the roughness profile from the mean line. I sent my customer’s project manager an e-mail outlining the agreed upon smoothness specification in detail and asked him to send me his approval note for this TBD specification. After I received his approval note, I initiated an engineering change order for the project specifications in our document control system. I distributed the final smoothness specification to all the engineers and manufacturing people who were involved with the stainless steel surfaces. I also sent a copy of the released project specification to my customer’s project manager. One by one, we negotiated and agreed on all the TBD specifications. One of these specifications was the interface drawings that were supposed to be delivered to us after four weeks from the start of the project. It took them six weeks to deliver the interface drawings to us. We were lucky to receive them in six weeks and fortunately, they did not affect the progress of my project. So I did not raise any ruckus with my customer about this crucial delay. I kept their delay as an ace in my pocket to exchange it with a future project delay that could have happened on our side. We finished all our stress calculations and system components designs on time. We as a team were ready for the mooring system design review. We had a two-day meeting at our facilities. During the meeting, the customer’s chief engineer told us that the slots that were designed into the mooring system were good for the chain passage, but they were not sized appropriately for the passage of the chain connectors. My team and I were quite surprised by this announcement by our customer, because the project specifications clearly identified the chain size and dimensions and also identified that there would be no chain connectors in this mooring system. I showed them their specifications. My customer’s team was embarrassed to realize their slip in project specifications. My customer’s project manager emphasized that we had to redesign the mooring system for the chain connector passage. The only solution was to evaluate the impact of this major change to our project for manpower, cost, and schedule. I asked my customer’s project manager to give me two days to analyze the effects of this major change and to provide him with a written revised proposal. He accepted my offer and they left our facilities after throwing a major twist into the project. We had to redo all of our stress calculations and change our design drawings. On top of it all, I was not even sure if all the designers on my team were available for the expanding project. I had a meeting with my team to get their time estimates for the customer’s new change order. I estimated the time and cost impact of the engineering change order to the project. I met with the managers of each member of my team regarding their availability for the extended project. After I had all the facts, I collected my upper management team for a meeting and showed them the impact of our customer’s change order. They made some minor changes to my cost estimates. I got the upper management’s blessing for the change order. Then I wrote a formal response to my customer’s project manager for their proposed change. The project was delayed by two months and this major slip in my customer’s specifications cost them 20% extra. My customer’s project manager discussed my schedule and cost impact on the project to their change order with his upper management. They had no negotiation leverage but to accept my proposal. The surprising change order was a major slip on their part. My team finished the project two weeks earlier than promised. My team’s efforts to finish the project two weeks early received excellent reviews from my customer’s project manager. Source: Atesmen, M. K. (2015). Project Management Case Studies and Lessons Learnt. Boca Raton: Taylor

Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more
Open chat
1
You can contact our live agent via WhatsApp! Via + 1 4129036714

Feel free to ask questions, clarifications, or discounts available when placing an order.

Order your essay today and save 20% with the discount code SOLVER